Advance loss of profits (ALOP)
Cover that pays the lost margin when insured damage during construction delays a project's start-up.
A transformer is damaged by fire during erection and a wind farm's commercial operation date slips by six months. The physical damage goes to the CAR or EAR policy. The revenue the project should have earned over those months goes to advance loss of profits (ALOP), also called delay in start-up (DSU). The cover pays the loss of gross profit, or on many lender-driven programs the debt service and fixed costs, that follows from a delay in completion caused by insured physical damage during construction or erection.
ALOP differs from ordinary business interruption at the starting point. BI indemnity runs from the date of the damage, for a business already trading. ALOP runs from the scheduled commercial operation date in the contract, because before that date there was no revenue to lose. A time deductible, counted in days of delay, comes off the front, and indemnity stops at the end of the indemnity period, measured from the scheduled date. In shorthand, indemnity = (min(delay, indemnity period) − time deductible) × insured gross profit per period, before any average for underinsurance.
Only delay caused by insured damage counts. A late permit, a contractor's insolvency, a grid connection that is not ready, or weather that stops work without damaging anything does not trigger it. Damage in transit is the classic gap. The Institute Cargo Clauses exclude loss caused by delay (clause 4.5 of the 2009 ICC), so a transformer damaged at sea needs a marine DSU cover written with the cargo policy for the delay to be paid.
Underwriters rate ALOP off the schedule. They read the critical path, the lead time on long-lead equipment (large transformers, turbines, subsea cable), whether spares exist, and the margin assumptions in the financial model. Lenders require it on project-financed deals because repayment depends on the first months of operation. On an offshore wind farm or a large power plant the ALOP sum insured can rival the physical damage value, and the indemnity period is usually set from the replacement lead time of the slowest critical component.
Take a solar plant scheduled to enter commercial operation on July 1, 2026, insured for a gross profit of €2 million a month (€2.5 million of expected revenue less €0.5 million of variable costs), with a 60-day time deductible, taken here as two months, and a 12-month indemnity period running to June 30, 2027. A fire on site in March 2026 pushes the start to January 1, 2027, six months late. ALOP pays (6 − 2) × 2 = €8 million, on top of the CAR claim for the physical damage. Had the start slipped to October 1, 2027, fifteen months late, indemnity would have stopped at the end of the period, at (12 − 2) × 2 = 20 million.
- Institute Cargo Clauses (A), (B) and (C), January 1, 2009, clause 4.5 (exclusion of loss caused by delay)
ALOP, advance loss of profits, DSU, delay in start-up, alop insurance, DSU insurance, delay in start up insurance, advanced loss of profits